Full 2L QBank
Social & Preventive Medicine Health education & planning 86074768

The critical path (CPM) method in health planning and management is -

A
The shoest time taken to complete the project
B
The midpoint for review of the project
C
The longest path taken to complete the project
D
Concerned with queuing theory
High-Yield Explanation
- Critical path method : the longest path of the network. - if any activity along the critical path is delayed, the whole project will be delayed. Reference : Park's textbook of preventive and social medicine, 23rd edition, pg no:872 <\p>

Related Social & Preventive Medicine MCQs

Practice 2,00,000+ NEET PG Questions Free

Timed mock tests, mistake queue analytics, audio lectures & zero attempt limits on i❤️Exams.

Start Free Mock Test Now