Critical path takes -

A
Maximum time
B
Minimum time
C
Intermediate time
D
None
High-Yield Explanation
- Critical path method : the longest path of the network - if any activity along the critical path is delayed, the whole project will be delayed. Reference : Park's textbook of preventive and social medicine, 23rd edition, pg no:872 <\p>